Day 2

Counters have been partially torn down, flooring and sub floor partially torn down. Pantry (new and old) placed in their new locations, along with the fridge. New base cabinets and wall cabinets in their new locations as placeholders. Electrical work is complete, with the installation of can lights and a pendant light. Also, electrical overload switches installed to bring the kitchen up to code. Trim work on the utility room and entrance doors completed. Trim work starting to be torn down on the garage door but that might have to wait until floor is started. Electrical stove has been disconnected.

Appliance store confirms delivery of sink and stove tomorrow. Hood is still not in stock. No ETA.